Townhouses Well Underway at Hamilton Hill

The 54 Townhouses in Stage 1 of Hamilton Hill, Woodforde are making excellent progress, with some key stages either completed or well underway.

These include:

Townhouses 56-69
• Foundation slabs have been poured

Townhouses 65-69
• Lower wall frames are in place
• Floor frames and windows installed with scaffolding erected

Townhouses 67-69
• Hebal cladding and partition walls are completed
• Upper level framing has started

Townhouses 41-53
• Footing excavations have begun

Foundation works are due to commence shortly for Lots 72-96 – watch this space!

 

For information on remaining townhouses available in Stage 2, please contact 8110 9800 or Hamilton Hill website.